Work Breakdown Structure and Sequence of Work

The project team should be concerned with the effectiveness as well as the efficiency of the project. Effectiveness will be enhanced if there is more of an overlap in the roles played by design and construction so that each individual player may take action in the light of a greater understanding of client requirements.

2.3 Sequence of Work

Table 2.1c Courtesy: (Chudley and Greeno, 1999) Sequence of work for building construction

NO SEQUENCE OF WORK

SUBSTRUCTURE WORK

1 FOOTING

2 Caisson Excavation

3 Drilling Cassion

– 4 Prefabricated Steel Casing

– S Installation Temporary Steel Casing

6 Remove water from Hole

– 7 Installation Reinforced Bars

8 Pouring Concrete Work

9 Concrete Vibration

10 FOUNDATION

Table 2.1c: Continued

ii Positioning Formwork

12 Prefabricated Reinforcement Bar

13 Installation Reinforcement Bar

14 Pouring concrete

15 Concrete Vibration

16 Curing Process

17 Striping Concrete Formwork

18 GROUND FLOOR BEAM

19 Positioning Formwork

20 Prefabricated Reinforcement Bar

21 Installation Reinforcement Bar and Plumbing

22 Pouring concrete

23 Concrete Vibration

24 Curing Process

25 Striping Concrete Formwork

26 GROUND FLOOR SLAB

27 Cleaning of Slab Form

28 Positioning Formwork

29 Prefabricated Base Reinforcement Concrete (BRC)

30 Installation of Base Reinforcement Concrete (BRC)

31 Pouring Concrete

32 Concrete Vibration

33 Curing Process

34 Striping Concrete Formwork

SUPERSTRUCTURE

1 GROUND FLOOR COLUMN

2 Prefabricated Steel Cage of Column

3 Installation Steel Cage

– 4 Column Rebaring

5 Column Plumbing

6 Cleaning of Column Form

7 Positioning Formwork

8 Pouring Concrete

9 Concrete Vibration

10 Curing Process

11 Striping Concrete Formwork

12 STAIRCASE CONSTRUCTION

13 1 Positioning Formwork

I

Table 2.1c: Continued

Prefabricated Steel Reinforcement Bar

T15 Installation Reinforcement Bar

Poured Concrete

Read also  The Cinderella Of The Building Industry Construction Essay

17 Concrete Vibration

18 Curing Process

– 19 Striping Concrete Formwork

20 GROUND FLOOR LEVEL WALL

CONSTRUCTION

– 21 Installation of reinforcement bar(wall height more

than3m)

22 Mortar mixed

23 Concrete Block Lying

24 ROOF CONSTRUCTION

25 Prefabricated Roof Trusses at Plant

26 Installation of Roof Trusses

27 Installation of Roof Membrane

28 Installation of Roof Covering

INTERNAL CONSTRUCTION and FINISHES

1 DOOR

2 Prefabricated Door

3 Installation of Door

4 WINDOW

5 Prefabricated Window

6 Installation of Window

7

PLASTERING

8 Gypsum Mixing

9 Installing the Wall Plaster

– 10 ROOF CEILING

11 Prefabricated Ceiling

12 Installation of Ceiling

13 PLUMBING

12

13

Table 2.1 c: Continued

GROUND FLOOR COLUMN

15 Prefabricated Pipe for Plumbing Work

Installation of pipe

17 Pipe Fitting

18 ELECTRICAL WORK

19 Prefabricated Electrical Accessory

20 Wiring Work

21 Installation of Electrical Accessory

22 PAINTING

23 Wall painting

For the structure above the ground level, the sequence of work for the

construction process just repeated the super structure work above and the sequence of

work will be repeated until the project complete.

2.4 Work Breakdown Structure (WBS)

Work breakdown structure is a process of dividing the project task into smaller

manageable components for planning purpose. A complex project is made manageable

by first breaking it down into individual component in a hierarchical structure, known as

the work breakdown structure (WBS). The WBS is the structure which defined task,

facilitating resource allocation, assignment of responsibilities and measurement and

control the project. The WBS is widely use by the project manager as a tool in the

planning activity for the construction project (Newitt, 2005).

Read also  Building Design Process

14

The Work Breakdown Structure (WBS) is a key planning tool used to define a

project in terms of its deliverables, while providing a method for breaking down those

deliverables into meaningful work efforts. The WBS enables project managers to clearly

describe the hierarchical nature of work to be performed. The WBS also establishes a

foundation for other elements of the formal project plan. Project managers regularly are

challenged to clearly describe desired project outcomes to all involved, while they also

capture the order and sequence of the work necessary to produce those outcomes. Once

it is complete, the WBS becomes an essential building block and reference point for

other project plan components. (Newitt, 2005).

2.4.1 Use of Work Breakdown Structure (WBS)

Some companies prefer to use WBS to help identify the activities prior to

developing the schedule. This is systematic means of defining the activities so that each

activity can be readily identify by its WBS number. The WBS numbers builds

intelligence into the activity ID number. The numbering system is typically unique for a

company or project. Some prefer to divide the project by the responsible person, firm, or

subcontractor. Others divide the project or break it down according to the building or

area of work. Sometimes it makes sense to break it down according to the divisions in

the specification. A common method is to break down the project according to phases.

(Newitt, 2005).

For example with a building, start with the major phases of the project and number them

accordingly:

Phase I Project Feasibility

Read also  Pervious concrete and traditional concrete

Phase 2 Design and Engineering

Order Now

Order Now

Type of Paper
Subject
Deadline
Number of Pages
(275 words)