Project Management of the Opening Ceremony of the Commonwealth Games
1. Executive Summary
The project plan is for the the forth coming Common wealth games scheduled to be held during the months of July August in 2014, in Glasgow. The official handing over will take place on the 14th of October 2010,when Delhi in India will handover officially to the city of Glasgow in Scotland, thus appointing Scotland as the Host country for the 2014 Common Wealth Games. It is to be noted that this event “will be the largest multisport event ever to be held in Scotland”
Thus this report includes only of the opening ceremony’s Schedule plan, resource allocation and the cost to be effect.
2. Project Introduction & scope
The recent growth of multi sports as an industry around the world means that the management can no longer be commercials. Events such as the commonwealth games, have a large impact on their communities and, in some cases, the whole country. Thus it is a must to keep in mind throughout the planning process that this is the first time the country is hosting such and event and it shall have an impact to the country.
This is a service based scheduling project according to that the initial concern which I will propose will have the following scope which is needed to be completed to be successful in this event’s opening ceremony.
Events
Prepare the Events list
Find the Human resource by events
Find the Items the need in each resource (Dress, Transport and etc..)
Analyze the risk and exciting of event with professionals
Find the time of event execution
Check the events identification (Traditional,etc)
Security
Check the security availability in the location need to be allocate
Prepare high security zone in VIP guest
Facilitate the vehicle parking
Opening ceremony All task Analyzing
Location & Guest
Prepare the chairs and audience resource
Entrance and Exit point
Guest area allocation
Food and beverage
invitation
Schedule & Time table
Event list preparation
Allocate Resource to events
Allocate time to each and Every time /prepare schedule
Media
Invite an media
Provide a food and beverage
Supply the technical need (internet, power)
Facilitate an location in ground area
Physical resource
Electricity
Event Items
Professional support
3. Objective
To find all resource on time:
Accurate time estimation is vital in project management. The two main reasons for estimating time is vital as: Time estimates drive the setting of dead lines for delivery of project and also the determination of pricing of projects and its profitability can be estimated.
Thus finding all resources on time is very essential to carry on the project without delay as timing is important in an event like this as it has international criticism later on.
To allocate funds according to budget
Allocation of funds according to budget is a vital aspect, as it is an important tool needed in running a business in a proper manner. The allocation of funds should be done in such away that each responsible person can run the area smoothly without any interruption.
To schedule all ceremony event on time without any delay
Scheduling all events without a delay is very important as any delay occurring can cause disruption and run to high criticism. Prior to the main event rehersaling of the event should be done. When the rehersaling is done each aspect should be rehearsed without leaving out any event. Thus the above could be avoided.
Reduce events errors
Facilitate all participant to good service
A specialized committee should be allocated the above task, of looking into the needs of the participants and giving them the best service. It is a must to keep in mind this is the event of the participants rather than the spectators. Allocation of physical force is a must to keep the reduction of the above.
4. Measure of Successful level and Recommendation for Each task /Plan and out comes
Design/plan
Execution
Initiation
Testing
1. Event & activity design
2. Design Dress
3. Allocate the physical resource (music, Dress, Light)
4. Train the persons
5. Task allocate (Sub con)
1 proposal submission
2. Get quotation form 3rd party
3. Prepare the schedule
4. Find the resource
5. Evaluation and selection
1 .Events & Activity test with time
2. Physical resource test
3. Schedule test with time
4Recovery test (Disaster)
1 Fixed the date & time for each activity events
2. Fix all resource on time (physical & human)
3. Execute according to tested schedule
Opening Ceremony
1. Schedule monitoring and evaluating report
1 .Events & Activity test Report with Reasal
2. Physical resource test Report
3. Schedule test with time test report
4. Recovery test plan (Disaster)
1 proposal Acceptance
2. Budget Approval
3. Schedule and Activity and Event Report
4. Resource Supplier report
1. Design Aspect of event and activity (Document and Demos)
2. Design Dress (Dummy)
3. Allocate the physical resource (music, Dress, Light) Demonstration
4. Train the persons plan and schedule
5. Resource plan and resource requirement
5.1 financial requirement analyses
5.1.1 Budget for the opening ceremony
Overall opening ceremony should be allocated in 800 million. In Glasgow 2014 Common wealth Games committee, (Reference in: organization committee Budget allocation document)
According to allocated overall budget allocation in 800 Million we will propose our proposal profitability of our plan would be quite satisfactory.
5.2.1 Variable cost breakdown and overall total
This allocated budget should be dividing via the major Task event wise. This variable cost breakdown is based on the already allocated budget.
Here is the variable cost breakdown:
(All the values based on Millions)
Variable cost breakdown
Task/Event
Actual cost
Allocated cost
Staff cost
100
100
Events cost
200
250
Media cost & Entertainment
25
25
Security
50
55
Location &Guest
10
15
Food & Beverage
100
120
Transport
150
160
Total
635
755
Analyzing of the cost estimation:
Here graph is explained all the variance in allocated cost and actual cost variance.
1 .Staff cost is fixed as I will explain it further in the organizational chart how the staff should be allocated in the project. After analyze I will fix the cost.
2. Event cost is variance because some creative events, equipments and rehearsal cost should vary, that the main reason to increase an additional 50 for it.
3 Media cost should be fixed. There should not be any risk for it
4. Security, food and transport cost should add some additions .because these are depended on the guest and humans to be involved their activities.
Finally analyse all the expenditure additionally allocate a 120 Million for the risk factor wise.
This should be variance cost for this.
5.1.3 Revenue breakdown and overall total
Since the ceremony revenue is coming in as fallowing category based.
Ticketing
Suwannee’s and & Advertisement
Ground banners and Advertisement
Sponsors
Additionally in country has non profitable benefits on tourism.
Total estimation is all the earnings should be 130 Million.
Finally revenue should be in 175 Million.
5.2 physical requirement analyses
Physical resources Allocation:
Location & its resource
Allocation of resources will be predicted according to the requirements. Initially we analyze the location and its requirement. Location already decides and its resource should be available. Only need to identify repair and reconstruction points of it. After initial assessment all the reconstruct part and modification done by government .that mean I am not going to put its cost and allocation, Because it’s up to commonwealth standard achieving through the under supervisor on government and Olympic committee.
Ceremony Entertainment and Events
Other Ceremony entertainment and cultural and traditional events some expectation in physical equipment items, this is contributing with the one of sub contractor and service provider. Already that ceremony entertainment and event design committee proposal send to sub contractors to get quotation from them. It’s basically going under the allocated budget. Because initial easements already done by entertainment and event committee.
Services and Supply
All other services should be contracted out to sub party. All sub contactors and their services should be evolved by physical resource evaluation committee. Food, transport, security, Entertainment an equipment supliers, electricity…etc… All these suppliers have to submit their proposal under evaluation committee satisfactory.
Standards and Quality of services:
This part should be maintained by the commonwealth country sports comate members. Their already provide the standards which have to be maintain for us. Evaluation committee evaluate all these under maintain of these standards.
5.3 Human resource requirement analysis
We get divide in major in all HR resource in two categories. One is Project staff and organizing committee other one is out sauce persons who are the consult of the Events and activities. All the outsource consultants are working with us a part time.
5.3.1 Work break down structure
Opening ceremony
Food and Beverage
Resource
Events & Activity
Location and Ground Requirement
Decoration
Physical resource
Furniture
Traditional Dance
Human resource
Event items
Events Actors
Creative Dance
Power
Music items
Music
Dancers
Water
Lightning relevant Event
Area special feature
Ground Decorate
Singers
Musicians
Power supplier
Security
Ground suppliers
Designers
This work break down structure should be view ad all Major activity tasks have to do in this ceremony process. This may provide a series of work brak downstrcture for planning and all implementation Events in ceremony.
Each and every circumstance of the ceremony project and objectives this should be evaluated.
This is providing a benchmark by which quality for the project process can be assessed and level can be successful.
6. Scheduling and Time plan
6.1 Recommended timings from October 2014 to the opening ceremony
We are plan out to start as 15th of Arial 2014 in the project. We can finalize it 20 the July2014. If it can be execute 23 July 2014 to on word. Execution plan is 2 days final set up preparation .and Ready for final execution on opening ceremony on 23rd July 2014
6.1.1 Gantt chart and Key Milestone
6.1.2 Risk Analysis in Time Frame
We decide to finish all the work and ready for ceremony in 1st 20 the July2014. That mean we handle finally 3days risk mitigation on the final execution.
And other thing is most of the activity task going on par rally. Not depend on other task .that plan should be mitigate the time risk of the project.
And other thing in Resource evaluation and physical resource allocation we get finish mid of September. Lighting, music, ground setup, activity basic set up. That is very impotent to reduce the Technical risk and the man power risk and also can mitigate the Disaster recovery in the ceremony time.
7. Task and Person allocation
7.1 Task and allocated Team Structure
7.2 Organizational Breakdown structure
Project manager
Supply manager
Program manager
HR manager
Coordination manager
Admin coordinator
HR supply assistant
Event and Activity Designer
Resource finder
Evaluation Committee Coordinator
Service supply assistant
HR coordinators
Media coordinator
Security Coordinator
Physical resource supply assistant
Project manager
Food & Beverage coordinator
Secluded and Time maker
Physical resource coordinator
Additionally have a consultant on the ceremony event and activities as fawning professionals
Artifact and designs
Lighting
Sounds
Dancing and songs
8. Work procedure
8.1 Procurement management approaches
The Procurement management plan should be defined to clearly identify the all task and the responsibilities for Procurement from the beginning to the end of the project .The project manager will work with the project team, contractors, supply department, and other key players to manage the Procurement activities. In order to our team structure all the managers (program, HR, Coordination and supply) responsible for their department wise activities to beginning to end of this project.
Every department should be submitting their request as fallowing format. Supply manager have to be responsible to check with purchasing for each and every Items and service.
Item/Service
justification
needed by/ date
Authorized to approve purchases for the project team:
Project manager : warnapriya wijesundara
Supply Manager : Lasantha balasuriya
Purchasing officer : nalin weerasingha
8.2 Contractors and subcontractors managing
Then first step in the contract approval process is to determine what items or services will require Procurement from outside. Then each and every department managers need to request what are they need service and items from project manager. Manager will evaluate it with an head of department managers and suplymanager the call to get quotation from out side vendors. And also need to finalize this with evaluation committee members with Olympic committee member in commonwealth.
Vendors must have as fallows:
Before start all the contractors should be need to register in the government ministry of import and export and construction in Scotland.
Vendors have to submit their proposal include their service, cost and Items and their history of customers.
All the Item and service need to up to evaluation committee standard.
8.3 Standard of maintain sub contractors Evaluation for Each project
This section will explain the evaluation for the each and every service with vendors. Based on the following decision criteria Procurement manager, project manager, Purchasing manager and the international committee member evaluate all service and Items: Here is the area as we get evaluate:
Ability of the vendor to provide all items by the required delivery date
Quality
Cost
Expected delivery date
Comparison of outsourced cost versus in-sourcing
Past performance
9. Conclusion
To conclude this proposal this project based on organizing the opening ceremony on Glasgow 2014 Commonwealth Games we will estimate all based on as initially 800 Million Dollars. After revenue analyzing we will think to take a 135 Million. As our suggestion is it can be done 755 Million.
Our risk factor is 120 Million. The 120 Million is vary on the Glasgow 2014 Common wealth Games evaluation committee suggestion and request.
This shows that the ratio of profitability of our plan would be quite satisfactory.
Order Now